Set up company calendar

  • 4 minutes to read

In a work center group calendar, the working days / hours, shifts, public holidays and absenteeism are specified, which determine the available gross capacity of the work center group (measured over time) according to its defined effectiveness and capacity values.

A fundamental step in calculating a specific work center calendar is setting up one or more general company calendars. In a company calendar, a standard work week is defined according to the start and end times of each work day and the schedule of each shift. In addition, the fixed public holidays for the entire year are defined in the company calendar.

The following describes how an alternative work center calendar is set up. The steps are similar for setting up work calendars.

Create working layers

  1. Choose the icon out, give up work shifts and then choose the related link.
  2. On a blank line, enter a number in the box code to determine the layer, e.g. B. 1.
  3. Enter in the field description a description of the layer, e.g. B. 1st layer.
  4. Optionally, fill out lines for a second or third shift.

Even if your work center groups do not work in different shifts, enter at least one shift code.

Set up a company calendar

  1. Choose the icon out, give up Company calendar and then choose the related link.

  2. On a blank line, enter a number in the box code to determine the company calendar.

  3. Enter in the field description a description for the company calendar.

  4. Choose the Working days Action off.

  5. On the website Company calendar working days determine a whole working week with the start and end times for each day.

    Select in the field Shift code one of the layers you defined earlier. Add a row for each work day and shift. Example:

    Monday 07:00 15:00 1
    Tuesday 7:00 am 3:00 pm 1

    If you need a company calendar with two shifts, make an entry as follows:

    Monday 07:00 15:00 1
    Monday 15:00 23:00 2
    Tuesday 7:00 am 3:00 pm 1
    Tuesday 15:00 23:00 2

    All days of the week that are not defined in the company calendar, e.g. Such as Saturday and Sunday are simply considered non-working days and they have no available capacity in the work center calendar.

    When all the working days of a week are defined, you can use the page Company calendar working days close and continue entering public holidays:

  6. On the website Company calendar select the company calendar, and select the public holidays Action off.

  7. On the website Company calendar holidays Now define the public holidays of the year by entering the start date and time as well as the end date and time as well as a description of the respective public holiday in individual lines. Example. Example:

    07/04/2014 0:00:00 23:59:00 Summer vacation
    07/05/14 0:00:00 23:59:00 Summer vacation
    7/6/14 0:00:00 23:59:00 Summer vacation

The defined public holidays have an available capacity of zero in the workgroup calendar.

The company calendar can now be assigned to a work center in order to calculate a work center calendar, on the basis of which the entire work cycle planning for the time of this work center is carried out.

Calculate a work center calendar

  1. Choose the icon out, give up Workplace groups and then choose the related link.

  2. open the workstation that you want to update.

  3. On the Planning FastTab, choose in the field Company calendar code select the calendar that is to be used in this work center as the basis for a work center calendar.

  4. Choose the action calendar out.

  5. Click on the side Workplace group calendar on Show actions, matrix.

    The workstation groups that have been set up are listed on the left of the matrix page. On the right there is a calendar in which the available capacities per working day are specified in the defined unit of measurement, e.g. B. 480 Minutes. Each line represents the calendar of a work center group.

    Note

    You can also display the capacity values ​​per week or month by making the selection in the field View after on the Matrix Options FastTab on the page Workplace group calendar to change.

    In order to reflect the new company calendar as a line in the selected workgroup, it must first be calculated.

  6. Choose the action to calculate out.

  7. On the info register Workplace group you can set a filter so that the calculation is only carried out for one work center group. If no filter is set, all existing work center calendars are calculated.

  8. Specify the start and end date of the calendar period to be calculated, e.g. B. a year from 01/01/2014 to 12/31/2014.

  9. Click the button OKto calculate the capacity.

Calendar items are now created or updated and show the available capacity per day or other period, according to the following three sets of master data:

  • The working days and shifts defined in the assigned company calendar.
  • The value in the field capacity on the workplace group card.
  • The value in the field effectiveness on the workplace group card

The calculated work center group calendar now determines when and how much capacity is available in this work center group. This controls the detailed planning of operations that are carried out in the work center.

Record absenteeism for work center groups

  1. Click on the side Workplace group calendar on Show actions, matrix.

  2. Select on the side Work center calendar matrix the work center group and the calendar day on which the absence should be recorded, and then click on Linked information, planning, absenteeism.

  3. Put on the side window Absenteeism Set the start and end times for absenteeism that day, and provide a reason. Example:

    01/25/01 8:00 AM 10:00 Maintenance

  4. Choose the To update Take Action, and then close the page Absenteeism.

The capacity of the selected day has now been reduced by the recorded absence.

See also

Set up a base calendar
Set up workplaces and workplace groups